Conclusion

Sample Time Frame:

  • Approx 2 years for site evaluation and research
  • Approx 4 years to obtain permit
  • Anywhere from 2 – 5 years for construction of Phase 1 (turbines and substations), based off projects of similar size in Europe
  • 5 years study period to determine whether or not to proceed with Phase 2
  • Additional 2 – 5 years for construction of Phase 2